Bug #289: 4. COmpetition Menu Organisation CMS
Feature #297: Podcast structure
Bug #300: 3. podcast - mobile tweaks
Bug #312: 3. sponsored by image
Bug #316: 3. Subscribers
Feature #317: Add website to homescreen
Bug #327: 2. Infinity Scroll not kicking in - review landing pages
Bug #331: 3. Schema - feedback
Bug #347: 3. CMS - competitions commenting
Bug #350: 4. topic + actual recommended pages
Bug #351: 3 article cache
Bug #360: 3. Amp Issues-feedback
Bug #365: InContent - Mobile
Bug #366: Ads - InContent
Bug #376: 2. gsc - error
Bug #379: 2. Topics Pages
Bug #380: 2. Tags issue
Bug #383: Ad Units display and delivery - Ads not showing
Bug #384: Ad Units display and delivery - homepage ads missing
Bug #388: 2. motherboard block missing
Bug #391: 3. missing schema
Bug #393: 1. instagram not showing

Status

Feedback
New
Feedback
New
New
New
New
New
New
New
New
New
New
New
New
New
Feedback
New
New
New
Feedback
New

Priority

Normal
Normal
High
High
High
Normal
Urgent
High
High
Normal
Low
High
High
High
Urgent
Urgent
Urgent
High
High
Urgent
High
Immediate

Updated

09/16/2019 09:18 AM
07/29/2019 11:10 AM
08/14/2019 04:03 PM
08/14/2019 03:54 PM
08/14/2019 03:52 PM
08/09/2019 03:32 PM
09/17/2019 02:28 PM
08/14/2019 03:39 PM
08/14/2019 03:24 PM
09/16/2019 08:53 AM
08/20/2019 11:13 AM
09/16/2019 09:11 AM
08/16/2019 03:29 PM
08/16/2019 03:30 PM
09/16/2019 08:48 AM
09/04/2019 12:38 PM
09/30/2019 02:17 PM
09/05/2019 12:25 PM
09/05/2019 12:26 PM
09/16/2019 08:40 AM
10/14/2019 03:53 PM
09/25/2019 01:49 PM
 
 
41
42
43
44
45
46
47
48
49
50
51
52
53
1
2
3
4
5
6
7
8
9
10
11
12
 

Also available in: PDF PNG